M Building Washroom Renovations

M Building 1st, 2nd, 3rd floor washrooms

Description of Event:

Renovations to M building washrooms will commence on March 2nd and will be completed over three phases, finishing at the end of March 2015. The majority of the work will be conducted after business hours in order to minimize disruption to building occupants. Areas under demolition and construction will be sealed off to block off dust and noise etc.

At intervals space will be out of service and signage will be posted to reflect these disruptions. Your patience during these renovations is appreciated. Please see the schedule below…

Phase one

  • Men’s washroom on 1st floor
  • Women’s washroom on 1st floor 
Phase two
  • Men’s washroom on 3rd floor 
  • Women’s washroom on 3rd floor

Phase three

  • Women’s washroom on 2nd floor

If there are any questions, please feel free to contact John Schroder, Manager, Maintenance and Operations North, at ext 4107.