Notice of Planned Hydro Service Interruption - North Campus

North Campus to be closed on Sunday, November 8, 2020

When Sunday, November 8, 2020 (all day)
Location North Campus – all buildings including the University of Guelph-Humber, Residences and the Arboretum/Centre for Urban Ecology
Purpose To perform work to support the Finch West LRT project including relocation of hydro poles on Hwy 27, and maintenance of electrical lines coming onto North Campus.

The Humber North Campus will be closed on Sunday, November 8, 2020. Students and employees will not be allowed entry into the College facilities (with the exception of Residence) during the hydro service interruption.

All mechanical and electrical systems across North Campus will be offline during the shutdown.

Central systems including Banner, Blackboard, Email and humber.ca will be available.

The Centre for Trades and Technology and the Education and Training Solution buildings (110 and 30 Carrier Drive) will not be affected by the hydro service interruption.

For more information or if you have questions, please contact Chris Nanos, Manager, Plant Services, at chris.nanos@humber.ca.