Building F Construction

September 12, 2014

On Monday, September 15, crews will start installing the curtain wall for the addition to Building F. Construction, which is anticipated to last until early November, will proceed in four phases to accommodate both the daycare and classes in JF.

The phases are:

  • Phase 1; east side of building (abutting HSF amphitheatre courtyard) – scheduled to begin September 15
  • Phase 2; west side of building (night shift construction) – scheduled to begin September 25
  • Phase 3; southwest corner of F building (alternate daycare entrance to be used) – scheduled to begin September 30
  • Phase 4; south side over JF building (night shift construction) – scheduled to begin October 13

While plans are in place to mitigate any noise or traffic flow issues, some of the work will be completed during the school day. We apologize for any inconvenience this may cause.

For more information, or to report any concerns, please contact Stephen Walo, senior project manager, at stephen.walo@mhpm.com.