REVISED: Power Shutdown - N Building (North)

July 17, 2015

Power Shutdown previously scheduled for July 17th, will now take place July 24th, 2015 at 11 p.m. 

Purpose: Power shut down required in order to install new electrical panel.

Temporary power shutdown required to install a new electrical panel required in N Building. Power will be out for approximately 4 hours, including lights and electrical outlets. 

Please note that emergency power will be available during this time. 

If you have any questions, please contact James Morgan, Project Coordinator, ext. 4428, with any questions.