Please be advised that on Tuesday, September 11, 2018 at 9 p.m. the CTI building contractor will demolish walls between the new CTI bridge and the 2nd floors of LRC and N buildings.
Date | Tuesday, September 11, 2018 |
Time | 9 p.m. to 6 a.m. |
Location | 2nd floor of LRC and N buildings |
Additional Details:
- This work is necessary to complete the connection between the new CTI building and LRC/N buildings.
- This work will be noisy using impact tools and equipment to create the necessary wall openings.
- Although the work is happening on the second floor, the noise will likely travel and be audible on other floors of the LRC and N buildings.
- All work will be done behind the construction hoarding already in place.
- All debris will be removed from the CTI bridge side of the hoarding.
- Contractor will employ measures to control dust migration.
- See attached drawing for location of demolition work.