Recent update as of August 25, 2022:
The Intersection at Kipling Avenue and Lake Shore Blvd W will be fully reopened by Saturday, September 3. Road work north on Kipling Avenue will continue until mid-September. View pictures of construction progress below.
Project contact:
For more information about this project please contact
Paul Martin, Communications Coordinator Capital Construction
paul.martin@toronto.ca | 416.392.3074
As part of the ongoing TTC Track Replacement and Road Reconstruction on Lake Shore Boulevard West and Kipling Avenue, disruptions are expected at Humber’s Lakeshore campus from mid-June to September. TTC bus service will be maintained both ways through the work zone, however some stops will be moved temporarily. Please plan your trip to account for any potential traffic delays.
See the map below for updated routes and TTC temporary stops:
Disruptions to Humber Lakeshore Campus
- The parking lot at the Fashion Institute will be closed during the duration of construction. Users of the Fashion Institute are asked to use the parking lot next door at the Medical Arts building.
- During the separate phases of the project noted below, there are traffic considerations for access to Colonel Sam Smith Park Drive.
What to expect
- A Paid Duty Officer will be on-site managing traffic, as needed.
- Due to the nature of this work, at times there will be noise and vibration around the work area.
- Please take extra care when walking near work sites, and always make eye contact with drivers before crossing in front of any equipment or vehicle.
- Thank you for your patience and we apologize for any inconvenience.
For more information and the latest updates: https://www.toronto.ca/lakeshorewestconstruction
TTC Track Replacement and Road Reconstruction on Lake Shore Boulevard West & Kipling Avenue
July 2022 to September 2022
Construction Schedule
Phase 1 |
TTC track renewal (top only replacement) on Lake Shore Blvd from Louisa Street to Mimico Avenue. |
July 4 to Aug 15 |
Phase 2 |
TTC track renewal (full depth replacement) at the intersection of Lake Shore Blvd W and Kipling Ave. |
August 2 to September 3 |
Phase 3 |
TTC track renewal (full depth replacement) on Kipling Ave north of Lake Shore Blvd, including Kipling Loop. Road reconstruction on Kipling Ave approx. 100m north from Kipling Loop. |
August 2 to mid-September |
Construction Hours
- Work will take place from 8 a.m. to 9 p.m., Monday to Friday.
- 7 a.m. to 7 p.m. on Saturdays or Sundays, as required.
- Prior notice will be provided if work extends into the weekends.
- There will be periods of 24-hour work by TTC crews during installation of new rail for each of the three phases.
- Construction updates will be provided.
TTC Service During Construction
- TTC bus service will be maintained both ways through the work zone, however, some stops will be moved temporarily.
Phase 1 - Lake Shore Blvd West - Louisa St to Mimico Ave - July 4 to Aug 15
Traffic Impacts |
|
Parking Impacts |
|
Pedestrian Impacts |
|
Phase 2 - Lake Shore & Kipling intersection - August 2 to September 3
In an effort to accelerate this project, the start date for phase two has been advanced. Preliminary work for the intersection closure has started.at the intersection of Kipling Avenue and Lake Shore Boulevard West. A full intersection closure at Kipling Avenue and Lake Shore Boulevard West will now take place from Monday, July 25 until Monday, August 1. Please see the attached Construction Update.
This intersection closure will take place as the work on Lake Shore Blvd W between Louisa and Mimico continues. Additional street signage is in place to notify westbound/eastbound drivers of the closure.
Traffic Impacts |
|
Phase 3 - Lake Shore/Kipling, Kipling Avenue and Kipling Loop - August 2 to mid-September
Traffic Impacts |
|